Projects

C-415 Mountain Loop Road

Cornfields, AZ – Road project took place April 13, 2020 – May 14, 2020. 1.2 miles was improved.

Improvements to C-415

Culvert Cleaning.

Sub-grade preparation.

Grade & Re-shape road.

Limestone placement.

Soil Stabilizer pending.

C-321 Gray Cactus Road

Tsaile, AZ – Road project took place March 2, 2020 – April 22, 2020. 1.5 miles was improved.

Improvements to C-321

Culvert/Drainage Ditch Cleaning.

Sub-grade preparation.

Grade/Re-shape road.

Limestone placement.

Soil Stabilizer applied.

C-429 South Balakai Road

Steamboat, AZ – Road project took place March 2, 2020 and is currently awaiting a soil stabilizer application. 1.0 miles was improved.

Improvements to C-429 South

Culvert/Drainage Ditch Cleaning.

Sub-grade preparation.

Grade/Re-shape road.

Limestone placement.

Soil Stabilizer pending.

C-302 Baldwin Road

Houck, AZ – Road project took place February 12, 2020 – May 5, 2020. 1.7 miles was improved.

Improvements to C-302

Culvert Cleaning.

Sub-grade preparation.

Limestone placement.

Soil Stabilizer pending.

C-296 Fort Defiance Road

Fort Defiance, AZ – Road project took place November 2019 – April 29, 2020. 0.6 miles was improved.

Improvements to C-296

Culvert Cleaning.

Sub-grade preparation.

Limestone placement.

Soil Stabilizer applied.

C-301 Silversmith Road

Houck, AZ – Road project took place September 9 – October 2019. 2.1 miles was improved.

Improvements to C-301

Culvert Cleaning.

Sub-grade preparation.

Limestone placement.

Soil Stabilizer applied.

N-9056 Besh Bi Toh Road

Jeddito, AZ – Road project took place July 29, 2019 – August 5, 2019. 3.0 miles was improved with the partnership of the Navajo Division of Transportation.

Improvements to N-9056

Culvert Cleaning.

Culvert Installation.

Limestone Build-up.

Dura-Blend applied.

C-273 Black Rock Acres Road

Fort Defiance, AZ – Road project took place March 7 – April 16, 2018. 1.0 miles was improved.

Improvements to C-273

Water Drainage Improved.

Unnecessary Limestone ripped.

Chip Seal applied.

Speed Bumps Installed.

C-455 MP-2 Blue Canyon Road

Fort Defiance, AZ – Road project took place October 31, 2017 – December 30, 2017. 4.6 miles was improved.

Improvements to C-455

Culvert Cleaning.

Culvert Installation.

Limestone Build-up.

Dura-Lock applied.

N-203 Kin Dah Lichi'i Olta Road

Kin Dah Lichi’i, AZ – Partnership road project took place July 27 – October 11, 2017. 2.6 miles was improved.

Improvements to N-203

Culvert Cleaning.

Limestone Build-Up.

Soil Stabilizer applied.

C-429 North Balakai Road

Steamboat, AZ – Road project took place May 8, 2017 – July 1, 2017. 3.0 miles was improved.

Improvements to C-429

Culvert Cleaning.

Culvert Installation.

Limestone Build-up.

Soil Stabilizer applied.